1.0 Objective: 

To establish a procedure for the destruction of rejected dies and punches.

2.0 Scope: 

This procedure applies to the destruction of rejected dies and punches used in the production department.

3.0 Responsibility: 

Officers and Executives in the Production Department

Managers in the Production Department

4.0 Procedure:

4.1 Destruction of Rejected Dies and Punches:

4.1.2 Inform the engineering department about the rejected die punches through an Inter Office Memo (IOM).

4.1.3 Hand over the rejected die punches to the engineering department.

4.1.4 Document all observations related to the rejected die punches in Annexure-I.

5.0 Abbreviations:

QA: Quality Assurance

SOP: Standard Operating Procedure

IOM: Inter Office Memo

References:

None

Annexures:

ANNEXURE – I: Rejected Punches / Dies Record